![]() |

Artist's Rendering of Kennedy Krieger Institute Clinical Research Building, 716 N. Broadway, that will house the Philips 7T Achieva MRI. The building will be located directly across Broadway from the Johns Hopkins Broadway Research Building, between the Metro station entrance and Madison Street. This is diagonally across from the KKI 707 N. Broadway Building where the Kirby Research Center's two 3T MRI's and offices are located. The 7T scanner will be housed in the north end of the basement level (toward Madison Street).
The 7T Magnex magnet used for this scanner is not self-shielding as are most superconducting 1.5T and 3T magnets used today in MR scanners. As a result a 440 ton (400 metric ton), 6 sided, steel shield box must be constructed to contain the magnetic field. This box forms the largest part of the MR examination room; there is an area of the exam room at the front of the magnet, that is outside the shield box called the RF Porch. Openings about 8 by 8 feet square in the front and back of the box allow passage into and out of the shielded area. The box walls are thickest (16 inches) at the center of the four walls that parallel the magnet's long axis (the 2 long sides and top and bottom), stepping down to 8 inches at the two ends. The steel used for the shield is an alloy that has high magnetic permeability and was annealed after the plates were formed and cut to size to further increase permeability. Since the magnet must be perfectly centered in the box, the box is sunken below floor level into the "MR pit". The bottom of the box is filled with concrete and high density foam blocks to form the floor the magnet sits on.
Due the the proximity of the Metro and heavy traffic on Madison Street and Broadway, the scanner needs to be isolated from vibrations. The entire MR examination room, including the 440 ton shield with it's infill, the 35 ton magnet and all exam room interior finishes will be suspended on a Hammond Kinetics air spring isolation system. Twenty-six pressurized air springs will lift the room approximately 1/4 inch providing complete isolation from outside vibrations. Three level sensors regulate the air pressure in the air springs keeping the room level.
The air springs were set into place on March 4, 2008
before the concrete base that sits on the springs was formed
and poured. This allowed use of a fork lift to move the 300
pound air spring units into place rather than having to move
them by hand and hoist down the pit access shaft. This
concrete base is shaped like a giant bathtub, with a bottom
and four sides that come up the sides of the pit the reach
the finished floor level of the basement. The bottom
approximately 4 feet of the steel shield box will sit in this
bathtub.
Space under the "bathtub" in the bottom of the MR pit,
allows access to service the air springs. This is reached via
a vertical shaft with ladder and hoist in case one of the air
springs ever needs to be replaced. The springs are arranged
in 4 rows down the long dimension of the scan room, one row
along the left and right walls and a double row down the
center. Access aisles run along each row.
| Fence in Parking Lot, Demolition & Grading | 09/18/07 | 10/05/08 |
| Drill Sheeting & Shoring Piles and Caissons | 10/09/07 | 12/03/07 |
| Mass Excavation of Building Basement | 12/04/07 | 01/10/08 |
| Construct MRI Pit | 01/16/08 | 02/29/08 |
| Install Airbags | 03/03/08 | 03/05/08 |
| MRI Room Slab | 03/06/08 | 04/03/08 |
| Pour Basement Slab & Walls | 03/28/08 | 04/08/08 |
| Install 440 ton Magnetic Shield | 04/16/08 | 06/02/08 |
| Erect Structural Steel | 06/03/08 | 08/12/08 |
| Pour Elevated Slabs and Rooftop Slab | 08/13/08 | 09/12/08 |
| Exterior - Masonry, Roofing & Windows | 09/04/08 | 12/01/08 |
| 7T Magnet ships from UK | 10/01/08 | |
| Install MRI RF Shield | 10/02/08 | 10/26/08 |
| RF Shield Test | 10/27/08 | |
| Rig and Set 70,000 lb. 7T Magnet | 11/22/08 | 11/23/08 |
| MRI Suite Framing, MEP & Finishes | 11/28/08 | 01/31/09 |
| Magnet Installation by Magnex/Varian | 01/29/09 | 02/27/09 |
| Cryostat vacuum | 01/29/09 | 02/02/09 |
| Cryostat pre-chill with liquid nitrogen | 02/02/09 | 02/08/09 |
| Cryostat fill with liquid helium | 02/10/09 | 02/16/09 |
| Magnet ramping to 7T | 02/19/09 | 02/22/09 |
| Magnet shimming | 02/23/09 | 02/24/09 |
| Cryocoolers off due to chilled water system failure | 02/26/09 | 03/06/09 |
| Magnet radiation shield cool down | 03/06/09 | 03/20/09 |
| Magnet persistance and boil-off checks | 03/19/09 | 03/20/09 |
| Magnet acceptance | 03/20/09 | |
| MR Equipment Installation by Philips | 01/26/09 | 03/27/09 |
| Cabinets placed and cabled, magnet room cabled | 02/02/09 | 02/18/09 |
| Magnet covers, patient couch placement | 03/05/09 | 03/11/09 |
| Power test & pre cals ECC | 03/23/09 | 03/24/09 |
| Gradient ECC | 03/24/09 | |
| RF coil tests | 03/22/09 | 03/25/09 |
| Final system calibrations | 03/25/09 | 03/27/09 |
| PTS data collection | 03/25/09 | |
| Operational 7T Scanner | 04/02/09 | |
| 7T Training | 04/06/09 | 04/07/09 |